Notice of Meeting:

I hereby give notice that an ordinary meeting of the Infrastructure Services will be held on:

 

Date:                                                    Monday 10 February 2020

Time:                                                   1.00 pm

Venue:                                                Edinburgh Room, Municipal Chambers,
The Octagon, Dunedin

 

Sue Bidrose

Chief Executive Officer

 

Infrastructure Services Committee

PUBLIC AGENDA

 

MEMBERSHIP

 

Chairperson

Cr Jim O'Malley

 

Deputy Chairperson

Cr Jules Radich

 

 

Members

Cr Sophie Barker

Cr David Benson-Pope

 

Cr Rachel Elder

Cr Christine Garey

 

Cr Doug Hall

Mayor Aaron Hawkins

 

Cr Carmen Houlahan

Cr Marie Laufiso

 

Cr Mike Lord

Cr Chris Staynes

 

Cr Lee Vandervis

Cr Steve Walker

 

Cr Andrew Whiley

 

 

Senior Officer                                               Simon Drew, General Manager Infrastructure Services

 

Governance Support Officer                  Jenny Lapham

 

 

 

Jenny Lapham

Governance Support Officer

 

 

Telephone: 03 477 4000

jenny.lapham@dcc.govt.nz

www.dunedin.govt.nz

 

 

 

 

 

 

Note: Reports and recommendations contained in this agenda are not to be considered as Council policy until adopted.

 


Infrastructure Services Committee

10 February 2020

 

 

ITEM TABLE OF CONTENTS                                                                                                                                         PAGE

 

1             Public Forum                                                                                                                                                              4

2             Apologies                                                                                                                                                                    4

3             Confirmation of Agenda                                                                                                                                        4

4             Declaration of Interest                                                                                                                                           5

Part A Reports (Committee  has power to decide these matters)

5             3 Waters Activity Report for the two Quarters ending 31 December 2019                                     17

6             Transport Activity Report for the Two Quarters ending 31 December 2019                                   26

7             Parks and Recreation Activity for the Period ending 31 January 2020                                              35

8             Waste and Environmental Solutions Activity Report for the two quarters ending 31 December 2019              41

9             Property Services Activity Report for the two Quarters Ending 31 December 2019                    51

10           Items for Consideration by the Chair                                                                                                             63

 

 


Infrastructure Services Committee

10 February 2020

 

 

1          Public Forum

At the close of the agenda no requests for public forum had been received.

2          Apologies

Apologies have been received from Mayor Aaron Hawkins and Cr Andrew Whiley.

 

That the Committee:

 

Accepts the apologies from Mayor Aaron Hawkins and Cr Andrew Whiley.

3          Confirmation of agenda

Note: Any additions must be approved by resolution with an explanation as to why they cannot be delayed until a future meeting.


Infrastructure Services

10 February 2020

 

Declaration of Interest

 

  

EXECUTIVE SUMMARY

1.              Members are reminded of the need to stand aside from decision-making when a conflict arises between their role as an elected representative and any private or other external interest they might have.

2.         Elected members are reminded to update their register of interests as soon as practicable, including amending the register at this meeting if necessary.

 

RECOMMENDATIONS

That the Committee:

a)         Notes/Amends if necessary the Elected Members' Interest Register attached as Attachment A; and

b)        Confirms/Amends the proposed management plan for Elected Members' Interests.

 

 

Attachments

 

Title

Page

a

Register of Interest

7

  



Infrastructure Services

10 February 2020

 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator

 

    



Infrastructure Services

10 February 2020

 

Part A Reports

 

3 Waters Activity Report for the two Quarters ending 31 December 2019

Department: 3 Waters

 

 

 

EXECUTIVE SUMMARY

1          This report updates the Committee on water, wastewater and stormwater operations, maintenance and capital works, including contracted out services.

2          Highlights for the two quarters include:

a)         Ross Creek Reservoir commissioning process is nearly complete.

b)        Southern Reservoir Spillway renewal is complete.

c)         Good performance against wastewater discharge resource consents.

d)        Continued decreasing foul sewer blockage trends.

RECOMMENDATIONS

That the Committee:

a)     Notes the Three Waters Activity Report for the six months ending 31 December 2019.

 

BACKGROUND

3          The water activity delivers the effective collection, treatment and reticulation of water. The wastewater activity provides the collection, treatment and discharge of water.  The stormwater activity encompasses collection and safe disposal.  All three activities are managed in a way that protects public health and minimises impact on the environment.

DISCUSSION

Management of Three Waters services

4          The collection, treatment, reticulation and disposal of drinking water, wastewater and stormwater are managed directly by Council.  The maintenance of the water, wastewater and stormwater pipe networks is contracted to City Care Limited.

5          The Council’s water supply service consists of four service areas: metropolitan Dunedin, and the three outlying areas of West Taieri, Outram and the Northern Schemes. These include some areas that are now fed from Mount Grand as well as the areas of Waitati, Warrington, Seacliff and Merton, Waikouaiti and Karitane, that are supplied from the Waikouaiti Water Treatment Plant.

6          The water supply network includes 21,000 hectares of water catchment; 1,386 km of pipeline; 28 pumping stations; 63 reservoirs (raw and treated) and 10 treatment plants.

7          The Council’s wastewater service consists of seven service areas including metropolitan Dunedin and six outlying areas: Green Island, Mosgiel, Middlemarch, Seacliff, Waikouaiti/Karitane and Warrington. The Metropolitan system takes the east and west harbour communities of Portobello and Port Chalmers respectively and discharges from Tahuna Wastewater Treatment Plant via the long ocean outfall. Green Island Wastewater Treatment Plant takes the treated Mosgiel effluent and discharges this along with wastes from Green Island, Abbotsford and coastal south Dunedin via the ocean outfall at Waldronville.

8          The wastewater network comprises 909 km of pipes, 87 reticulation pumping stations, 115 domestic pumping stations and seven treatment plants. The service is provided to approximately 107,000 residents and 106 trade customers.

9          The Council’s stormwater service manages the collection and disposal of stormwater to domestic and commercial residents in eight service areas, including metropolitan Dunedin and seven outlying areas: Brighton/Waldronville; Green Island; Mosgiel; Middlemarch; Outram; Port Chalmers; and Waikouaiti/Karitane and Warrington. The stormwater network comprises 372 km of pipes and 11 pumping stations.

Non-financial performance

Service

10        Figure 1: Total treated water network demand in millions m3 (production from all metro treatment plants)

11        Treated water consumption across the city has been average for the first two quarters of 2019/20. Moderate weather, the Deep Stream Catchment fire and associate usage behaviours have helped to reduce water demand.

12        Figure 2: Percentage response times met ≤24hours for all 3 Waters customer calls

Quarter1 - Ending 30 September 2019

Response Times Met

Wastewater

99/110

90%

Water

456/498

92%

Stormwater

11/13

85%

Quarter 2 - Ending 31 December 2019

Response Times Met

Wastewater

109/119

92%

Water

509/571

89%

Stormwater

21/23

91%

13        In Quarter 1 response times were met within the prescribed percentage of 90% for both wastewater and water. The stormwater response time is slightly below. Quarter 2 response times were met for wastewater and stormwater within the prescribed timeframe of 90%. The water response time for this period was 89%.

14        Figure 3: Number of customer complaints for drinking water

Customer Complaint Concerning

Number of Complaints (Quarter 1)

Number of Complaints (Quarter 2)

Continuity of supply

105

62

Drinking water clarity

11

4

Drinking water odour

1

2

Drinking water pressure or flow

15

33

Drinking water taste

 

 

Complaints about service

4

7

 

15        Drinking water complaint rates for the first two quarters have been lower than average for the first half of the year. Low incidence of frost in the winter and dry weather in the summer have contributed to this trend.

16        Figure 4: Number of wet weather wastewater overflows

17        For Quarter 1 and 2 there were 22 recorded overflows across all sites. Nine were at Kaikorai Valley Road and eight at Lindsay Creek.

Value & Efficiency

18        Figure 5: Number of water main breaks (12 month rolling average)

19        The watermain failure rate has been tracking downward for the last 3 years. Rates of failure have stabilised in the first half of 2019/20.

20        Figure 6: Average duration of unplanned watermain shutdowns in minutes

21        The trend of unplanned water shutdowns for Quarter 1 and 2 has been variable. Contractor resource availability and failure severity have contributed to the variable shutdown times.

22        Figure 7: Number of foul sewer blockages (12 month rolling average)

23        The number of foul sewer blockages has continued a reducing trend. It should be noted that recent blockage trends are largely caused by fat and wet wipes. Proactive cleaning of foul sewer pipelines has helped to continue to reduce the overall number of blockages in the foul sewer network.

24        Figure 8: Percentage wastewater discharge consent compliance.

25        Wastewater discharge compliance for Quarter 1 was 98.80%.  The compliance for Quarter 2 was 98.30%. Non-compliance was mostly caused by breaches of geomean limits caused by historic failed results, as well as an ongoing breach of a nitrogen limit at Warrington that the plant cannot meet.

26        Figure 9: Percentage planned maintenance completed

27        In Quarter 1 and 2, 2,560 Plant planned maintenance work orders were created with 2,234 completed orders, 329 unfinished orders and nil cancelled orders within the designated timeframes. City Care completed 100% of the 1,754 planned network maintenance work orders for Quarters 1 and 2.

Major initiatives

28        Reid Avenue and Carlyle Road Stormwater Pump Station (SWPS) Upgrades – The final design review has highlighted further project construction risks. Work to address these is underway. The flood management bylaw application is with the ORC for approval. The project estimate for costs to completion has risen to $14M.

29        Ross Creek Refurbishment Project – Stage 4 of the recommissioning programme is underway, raising the reservoir to 300mm above full supply level by placing sandbags across the spillway.  Final engineering assessments of the art installation are now complete, and fabrication of the stars is underway. The installation is expected to be completed in Winter 2020.

30        North East Valley 3 Waters Service Renewals – this project is an estimated $13M, four stage 3 waters renewals project to address old infrastructure in the North-East Valley and Opoho areas. Stages one and two are completed. Stage three is underway and is programmed to be completed in April 2020. The final stage is in procurement/RFT preparation for a July 2020 commencement.

31        Seacliff Wastewater Treatment Plant Upgrade – This project is to renew and upgrade an aged, small community wastewater treatment plant that services the Seacliff Community. Staff are working through the resource consent process and property purchase negotiations. Detailed design will commence once resource consent is confirmed.

32        Carlyle Road Pump Upgrades – This project is to renew existing pumps at Carlyle Road Stormwater Pump Station. Physical works are currently being tendered with construction expected to begin in February/March.

33        Rural WTP Upgrades – this project will upgrade existing water treatment processes at Waikouaiti and West Taieri Water Treatment Plants. A containerised filtration unit was purchased and has been delivered to the Waikouaiti Water Treatment Plant.  With further mechanical and electrical works to be implemented.  Completion of works at Waikouaiti is expected by the end of 2020 with West Taieri projected to be completed by the end of 2021.

34        Centre Street Silver Stream Bank Reinstatement – This project is to re-establish and armour the Silver Stream bank to protect the sole source of treated water to North Taieri. Physical works are currently being tendered with construction between March – April.

35        Southern Raw Water Reservoir Spillway Remediation Work – This project is to renew and upgrade the deteriorated spillway at Southern Raw Water Reservoir. Physical works are complete.

36        St Clair – St Kilda Coastal Plan – This project will involve engaging the Dunedin community to jointly develop a plan for the St Clair – St Kilda coast. The first phase of engagement will be focused on gaining community feedback on “what matters most” (values) – the bits of a place that a person comes to experience and the reasons they come back. The community will be informed of the challenges and opportunities in managing this coast, the history of the coast and the processes that shape it. The first phase of engagement will run from March - May. These community conversations will inform the latter part of our engagement process in June - September, where we will be engaging on “what can be done” (options) to manage this coast now and into the future.

OPTIONS

37        As this is an update report, there are no options.

NEXT STEPS

38        Areas of focus for the next quarter will be:

a)         St Clair – St Kilda Coastal Plan community engagement – beginning in March.

b)        Continued delivery of the 2019/20 capital programme.

c)         Tendering for the 2020/21 capital programme.

d)        Continued implementation of 3 Waters Asset Management Improvement Programme.

e)        Review and subsequent improvement of environmental performance.

f)         Understanding and engaging with the Central Government 3 Waters Review.

g)          Preparing and implementing changes to comply with minor changes to the Drinking Water Standards.

Signatories

Author:

Tom Dyer - Group Manager 3 Waters

Authoriser:

Simon Drew - General Manager Infrastructure Services

Attachments

There are no attachments for this report.

SUMMARY OF CONSIDERATIONS

Fit with purpose of Local Government

This decision relates to providing local infrastructure that is considered good-quality and cost-effective.

Fit with strategic framework

 

Contributes

Detracts

Not applicable

Social Wellbeing Strategy

Economic Development Strategy

Environment Strategy

Arts and Culture Strategy

3 Waters Strategy

Spatial Plan

Integrated Transport Strategy

Parks and Recreation Strategy

Other strategic projects/policies/plans

The Three waters activities support the outcomes of a number of strategies.

Māori Impact Statement

There are no known impacts for tangata whenua.

Sustainability

The 3 Waters activity contributes positively to the interests of the community by ensuring the provision of safe drinking water, and the safe and sustainable disposal of wastewater and stormwater.

LTP/Annual Plan / Financial Strategy /Infrastructure Strategy

The 3 Waters Activities are included in the Long Term Plan.

Financial considerations

The updates reported are within existing operating and capital budgets.

Significance

This decision is considered of low significance under the Significance and Engagement Policy.

Engagement – external

As an update report no external engagement has been undertaken.

Engagement - internal

As an update report no internal engagement has been undertaken.

Risks: Legal / Health and Safety etc.

There are no identified risks.

Conflict of Interest

No conflicts have been identified.

Community Boards

Any issues are discussed with the appropriate Community Board.

 

 


Infrastructure Services

10 February 2020

 

 

Transport Activity Report for the Two Quarters ending 31 December 2019

Department: Transport

 

 

 

EXECUTIVE SUMMARY

1          This report updates the Committee on Transport operations, maintenance, and capital works, including contracted out services.

2          Highlights for the period include:

a)         Physical works to repair the road network following the July 2017 rain event are completed.

b)        The construction of the Peninsula Connection Project continues with $10 million spent in the financial year to date.  Excellent progress has been made on section 2 between Vauxhall and MacAndrew Bay and section 7 at Turnbulls Bay.  Section 4 between Company Bay and Broad Bay is about to commence.

c)         Renewal programme is on target for full delivery, with $7m spent in the financial year to date. 

d)        The Transport Maintenance Contract is in negotiation phase with the preferred supplier.  The contract is to commence May 2020.

e)        Additional funding received from NZTA has allowed for the acceleration of further safety improvements in the minor improvements programme.

f)         Work continues to advance the progress of the major projects covering Our Streets, City to Harbour Bridge Connection, Tertiary Precinct and Shaping Future Dunedin Transport.

RECOMMENDATIONS

That the Committee:

a)     Notes the Transport Activity Report for the six months ending 31 December 2019.

 

BACKGROUND

3          The Transport activity provides the planning, construction, maintenance, and upgrading of the transport network. The network includes:

·      Roads.

·      Cycle ways.

·      Footpaths.

·      Bridges and retaining walls.

·      Street lighting.

·      Traffic signals.

·      Road marking.

4          The New Zealand Transport Agency (NZTA), the national road funding authority, provides a financial assistance subsidy for works that meet agreed criteria via the National Land Transport Programme.

DISCUSSION

Road Maintenance Contract

5          The Transport Maintenance Contract was tendered in early 2016 and awarded to Downer on 1 July 2016 for three years to 30 April 2020 and valued at $45 million.

6          A new maintenance contract was tendered for in July 2019.  The contract is for a 10-year period to April 2030.  At the time of writing this report a preferred supplier had been identified and Council are currently in negotiations.

7          A relevant, measurable, and robust performance framework has been developed in monitoring the current contract.  This focuses on key areas as follows:

a)         Service Delivery - Adherence to programme, specification, and budget.

b)        Value for Money – Delivering services efficiently.

c)         Customer Service – Improved customer experience across all aspects of the contract.

d)        Safety – Strict adherence to health and safety requirements and pro-active management of health and safety issues.

8          These key result areas and corresponding performance measures are being reviewed as part of the procurement of the new maintenance contract.  Key result areas under the new maintenance contract will have a stronger focus on sustainability in line with corporate policy of Council becoming carbon neutral by 2030.

Contract - Service Delivery

9          Performance is measured by network audit outcomes, adherence to programme delivery, and compliance with asset data and reporting requirements.

10        1,780 mud tanks have been cleaned this financial year to date. Routine cleans were delayed from March 2018 following the discovery of low-level asbestos traces in mud tank waste. Routine works have re-commenced with the contractor averaging 18 tanks per day.  It is forecasted that approximately 4,000 tanks, 48% of the network, will be cleaned this financial year.  The graphical forecast below is to end of current maintenance contract at 30th April 2020.

Contract - Value for Money

11        Performance is measured by inspection audits for work completed and the quality of claims.

12        Results in this area continue to be acceptable.  Claims made have been accurate with a robust contract monitoring processes in place to ensure payment is only being made when the work is completed to an acceptable standard. This remains the most effective method of ensuring required specifications are understood and consistently delivered.

Contract - Customer Service

13        Performance is measured by Customer Service Agency (CSA) response times and monitoring back log requests.

14        97.6% of CSA requests were programmed or completed on time in December versus a target of 95%. The largest volume of service requests continues to pertain to environmental clean-up issues requesting the clearing of debris and illegal dumping.

Contract - Safety

15        Performance is measured through Traffic Management Plan (TMP) audits, Health and Safety audit results, and valid complaints from the community. Results in this area have been acceptable over the two quarters. 

16        Sites deemed a ‘Pass’ or ‘Acceptable’ have few or no issues noted in the audit. A site deemed ‘Needs Improvement’ will require immediate mitigation to remain active. This is discussed by the auditor and the Traffic Management Controller on site. Any site deemed ‘Dangerous’ by an audit is immediately shut down.

17        Of the 11 TMP audits undertaken by DCC staff in December all sites passed.

18        Council has engaged the services of an independent Health and Safety adviser who is undertaking monthly health and safety site inspections. These are conducted in collaboration with Council and Downer staff.

19        The process of health and safety auditing is also designed to be a collective learning experience for the operational staff involved by raising awareness and knowledge of potential health and safety risks and appropriate process to mitigate them.

20        An independent health and safety report undertaken in December 2019 sited one minor non-conformance pertaining to the timeliness of STMS training records.  This is being addressed by the contractor.

Major initiatives

21        Capital Renewals 2019/20 – With a large proportion of renewal work procured and committed within existing contracts, Transport is on target to deliver Kerb renewals, footpath and carriageway reseal programmes.   Structural maintenance and retaining wall renewal contracts commenced February 2020 with completion estimated May 2020.  NZTA funding constraints are anticipated for 2020/21 which will impact the level of renewals that can be achieved.

22        Peninsula Connection Safety Improvement Project – Construction on Section 2 between Vauxhall and MacAndrew Bay is on track for completion mid-2020.  Section 7 which is the new retaining wall adjacent to the existing retaining wall at Turnbulls Bay is nearing completion and due mid-March 2020.  Section 4 between Company Bay and Broad Bay has started with survey and set-out work and construction commencing mid-February 2020.

23        Urban Cycleway Programme - The rail corridor portion of the urban cycleways project has been expanded to include the St Andrew crossing. Final approvals have been received from Kiwirail for the modified design and new funding secured for the remainder of the project. Final negotiations with the current contractor are nearing completion and work is expected to make a delayed start in March/April depending on resource availability. Completion will be mid to late 2020.

24        Our Streets - A period of consultation was run during July 2019 seeking feedback on nine arterial roads in Dunedin.  Almost 700 submissions were received via social pinpoint and online surveys.  The most common feedback related to safer crossing points, cycling and traffic speed management.  NZTA have endorsed the project for a Single Stage Business Case.  Consultants have been engaged to help develop the Single Stage Business Case and prepare concept designs for consultation. 

25        City to Harbour Bridge Connection - NZTA have advised they will accept a Single Stage Business Case, rather than a two stage (Indicative/Detailed Business Case).  This enables additional investigation work to be undertaken and ensures the programme remains on track.  A geotechnical investigations report and preliminary structure report have both been completed, as well an independent safety audit of the preferred alignment.  Traffic modelling will be undertaken as part of wider Dunedin central city traffic modelling in the coming months.  The next steps is to complete the Single Stage Business Case, including concept designs.

26        Tertiary Precinct - a period of consultation was run during September and October 2019. Over 1,000 submissions were received via social pinpoint, online surveys and events held in the Tertiary area.  Results have been summarised with most comments relating to pedestrian accessibility, greenery and parking.  NZTA has endorsed the project for a Single Stage Business Case.  A tender for professional services to help develop the Single Stage business case and prepare preliminary design is in the market.   

27        LED Street Light Installation – Installation is underway.  Approximately 200 lights have been installed to date predominantly in Middlemarch, Brighton, Outram and the Dunedin water front area.  The project has experienced delays due to resourcing issues which is being addressed with the contractor. 

28        Shaping Future Dunedin Transport- has developed two high level network scenarios through a process including a major workshop with key stakeholders on 14 November 2019, consideration of network options, assessment of urban realm quality and development of mode change options.  Both scenarios include far-reaching mode change programmes.  One scenario is based on retaining the one-way system while the other scenario proposes a two-way system.  Stakeholder feedback and further testing and refinement of the scenarios is planned in March and April.  The business case is expected to be complete and confirm a recommended scenario by mid-2020. 

29        Minor Improvement Projects (low cost, low risk projects) – Additional NZTA funding was made available and the budget was increased by $5.5M in late December 2019.

Low Cost/Low Risk projects completed or near completion in 2019/2020

a.         Central City School Cluster

b.         Sawyers Bay School road safety improvements

c.         Grants Brae School road safety improvements

d.         Maori Rd road safety improvements

e.         Variable School Speed limit signs (48 signs, incl. speed radar for monitoring)

f.          Great King St/Frederick St Barnes Dance conversion

g.         Kaikorai Valley Road Smart Pedestrian Crossing installation

h.         George St midblock signalised crossing safety improvements

i.          9 Schools Speed Limit temporary installation

Projects planned for completion in the National Land Transport Plan (NLTP) period (2019/20 and 2020/21)

a.         Blackhead Road footpath and roundabouts at Blackhead Rd/Tunnel Beach Rd and Blackhead Rd/Emerson St (Enhanced FAR rate of 71%)

b.         Forbury / Bayview / Allandale roundabout

c.         9 Schools Speed Limit installation incl. speed management.

d.         6 Schools speed management project

e.         Mobility crossings (2021 package)

f.          Road safety barrier package (2021 package)

Projects deferred to next NLTP

a.         Wharf Street / Roberts Street intersection upgrade

b.         Safety Improvements in Green Island town centre

c.         Footpath improvements in Mosgiel and Brighton

OPTIONS

30        As this is an update report, there are no options.

NEXT STEPS

31        Areas of focus for the next quarter will be:

·        Continue with the LED Implementation.

·        Continue to advance with the minor safety improvement programme.

·        Mobilisation of the new maintenance contract.

·        NZTA renewal funding for 2020/21 financial years.

·        Prepare for the next NZTA funding round for 2021/23.

·        Continue to advance with the major projects.

 

Signatories

Author:

Simon Smith - Asset and Commercial Business Analyst

Merrin Dougherty - Asset and Commercial Manager, Transport

Authoriser:

Simon Drew - General Manager Infrastructure Services

Attachments

There are no attachments for this report.

SUMMARY OF CONSIDERATIONS

 

Fit with purpose of Local Government

This decision relates to providing local infrastructure that is considered good-quality and cost-effective.

Fit with strategic framework

 

Contributes

Detracts

Not applicable

Social Wellbeing Strategy

Economic Development Strategy

Environment Strategy

Arts and Culture Strategy

3 Waters Strategy

Spatial Plan

Integrated Transport Strategy

Parks and Recreation Strategy

Other strategic projects/policies/plans

 

The Transport network supports a number of objectives across Dunedin City Council’s strategic framework.

Māori Impact Statement

There are no known impacts for tangata whenua

Sustainability

A well developed and maintained transport network will contribute to economic, social and environmental sustainability for Dunedin.

LTP/Annual Plan / Financial Strategy /Infrastructure Strategy

The Transport activities are included in the LTP.

Financial considerations

There are no financial implications

Significance

This report is assessed as having low significance in terms of the Council’s Significance and Engagement Policy

Engagement – external

There has been no external engagement in the drafting of this report.

Engagement - internal

There has been no internal engagement in the drafting of this report.

Risks: Legal / Health and Safety etc.

There are no identified risks

Conflict of Interest

There are no known conflicts identified.

Community Boards

Community Boards have an interest in the development and maintenance of the transport network within their area.

 

 


Infrastructure Services

10 February 2020

 

 

Parks and Recreation Activity for the Period ending 31 January 2020

Department: Parks and Recreation

 

 

 

EXECUTIVE SUMMARY

1          This report updates the Committee on Parks and Recreation operations, maintenance and capital works, including contracted out services, for the period 1 October 2019 – 31 January 2020.

2          Highlights for the period include:

a)         Freedom Camping season – With the assistance of Ministry of Business, Innovation and Employment (MBIE) funding of $161k, Parks and Recreation (PARS) staff have been working with DCC Regulatory and customer Service Agency (CSA) staff, in partnership with Department of Conservation (DoC) staff to plan and manage the summer 2019-20 season.  Joint DCC/DoC Ranger staffing has increased from 2 to 4 FTE this season, increased security patrols, temporary toilet facilities, and administrative support for CSA staffing, are all initiatives which are having a positive response to Freedom Camping management. 

b)        Predator Free Dunedin – Urban Linkage – Further to the signing of an agreement between Predator Free Dunedin (PDF) and DCC for the implementation of the Urban Linkage programme, 2 FTE Urban Linkage staff have been recruited and commenced work in mid-January.  PDF staff have recently moved into the Vergers Cottage, which means PDF staff are now all housed in one facility.  This will include DCC Urban Linkage staff.

RECOMMENDATIONS

That the Committee:

a)     Notes the Parks and Recreation Activity Report for the period ending 31 January 2020.

 

 

BACKGROUND

3          The Parks and Recreation activity provides public access to pools, urban green space, sports fields and facilities, recreation and leisure opportunities and a Botanic Garden of international significance.

4          Moana Pool is open year-round, with additional services including a creche, hydro slides, gym, physiotherapy, massage and a retail shop.  Mosgiel Community Pool is open seven months of the year and both the Port Chalmers Community Pool and St Clair Hot Saltwater Pool are open six months of the year.  In addition, the Council provides grants for the community pool at Middlemarch, Moana Pool and a number of school pools.

5          The Botanic Garden has 19 themed-garden collections and an aviary and is graded as a Garden of International Significance by the NZ Gardens Trust.

6          Council manages a wide range of open spaces providing parks and recreation facilities, for both organised and casual use, including playgrounds, sports fields, cemeteries, parks and walkways.  The maintenance of these spaces is contracted out, with Council staff overseeing operations including formal and informal lease/use arrangements and the development and implementation of policies and plans relating to parks and recreation. 

7          Parks and Recreation manage Moana Pool, Mosgiel Community Pool, Port Chalmers Community Pool and St Clair Hot Salt Water Pool.  The pools support casual swimming, professional swim coaching and learn to swim programmes.

DISCUSSION

8          Te Umu Kuri (Wellers Rock): This project originated from a letter to Council from Te Rūnanga ō Ōtākou Incorporated regarding concern about inappropriate use of Te Umu Kuri Wellers Rock and subsequent deterioration of the surface through vehicles eroding the landform.  A working party (incorporating PARS and Transport staff, Runanga, Otago Peninsula Community Board, and DoC) have been working closely and have agreed a practical solution. Rocks have recently been positioned on part of the isthmus, with the intention of restricting boat launching to one section and to allow for pedestrian only access to the rest of the isthmus.  Work is now progressing on updating and improving signage, and on leasing an adjacent parcel of land for parking to allow people to visit the area without parking on the road reserve.

9          Te Rauone:   Port Otago lodged a resource consent application with the Otago Regional Council (ORC) in early December for groynes and beach restoration work, and DCC staff (PARS and Transport) are working together to ensure work commences on building a new carparking area for the reserve in the first half of 2020.  The car park development will be phase 1 of the DCC reserve upgrade, and will ensure vehicles can no longer access the remainder of the reserve

10        Mosgiel Pool:   The project team (comprised of DCC PARS staff, Project Manager, Pool Trust, and Community Board representative) have been working on principles and requirement documents to support the tender process.  Work on the tender process has advanced, with initial market briefing planned for next month.  ORC resource consent was approved in late January to enable geotechnical ground testing work to be undertaken from February 18th.  It is expected that the geotechnical work will enable the site adjacent to the current pool site to be confirmed as the new pool development site.

11        Predator Free Dunedin – Urban Linkage:   Further to the signing of an agreement between  Predator Free Dunedin (PDF) and DCC for the implementation of the Urban Linkage programme, 2 FTE Urban Linkage staff have been recruited and commenced work in mid-January 2020.  PDF staff have recently moved into the Vergers Cottage, which means PDF staff are now all housed in one facility.  This will include DCC Urban Linkage staff.

12        Reserve Management Plans:  Parks Planning team are continuing to review the schedule of Reserve Management Plans reviews and prioritising which order these should be carried out.  The intention is to have a rolling schedule of Reserve Management Plan renewals so that they are updated every ten years.  Many are currently out of date.  The first two reviews are underway.  These are for the Botanic Garden and Truby King Reserve.

13        Reserves and Beaches Bylaw – A group comprised of DCC PARS and Comms and Marketing staff, DoC, and Community Board representative, have been meeting to consider options for increasing compliance with the Reserves and Beaches Bylaw.  Initiatives include utilising the joint DCC/DoC Rangers to educate and inform members of the community about the Bylaw, a full page advert taken out in The Star newspaper in November and working on updated signage for beaches and reserve. Other initiatives will be locally determined, and beaches and reserves will be prioritised according in line with the number of complaints and feedback Council staff receive.  At Tomahawk beach, work is about to get underway on developing and upgrading car parking and signage to attempt to encourage people not to drive on the beach.  At Long Beach, work was recently undertaken to place rocks around a portion of the reserve to protect it from vehicles.  

14        Asset Management – PARS staff have been working hard to develop a PARS Asset management Plan (AMP), and as part of this now have a 4 year conditional audit assessment contract in place to allow for regular assessments of all PARS equipment and facilities (excluding tracks).  This information will ensure significantly more accurate asset management planning to support future investment by Council.

15        Play spaces planning – PARS Senior Planner and the project team have made significant progress on a strategic plan for Playspaces over the period, and will be presenting their work to Community and Culture Committee on 11 February 2020.

16        Tracks planning – PARS Senior Planner and the project team have made significant progress on a strategic plan for Tracks over the period and have will be presenting their work to Community and culture committee in April.

17        Playground upgrades: Contractors have recently completed an upgrade of all Condition 5 (1 = best condition 5 = worst condition) play-ground equipment and softfall across the city.  Work is now commencing on upgrading all Condition 4 equipment and softfall, and this will be completed by 30 June 2020. 

18        Sports and Active Recreation Facility project – Work is about to commence on this important project which is a key component of the DCCs Parks and Recreation Strategy 2017-27.  This project will focus on developing a strategic approach to provision of Sportsfields and active recreation facilities and identifies gaps in provision for the DCC. The project will also provide a clear framework to guide the development of sport and active recreational facilities over the same period focusing on improving the quality, the experience, and establishing levels of provision.  The project team is currently forming and will include DCC PARS and Events staff, Sport Otago, Edgar Centre Manager, and Well South.

AQUATICS

19        Work on the Moana Master Plan project has progressed well in the last six months, and PARs staff have been working with BECA to develop a report that will support decision making on capital projects included in the current 10 year plan e.g. Hydroslide replacement, double glazing, and to inform the next 10 year plan.

20        Work commenced in January 2020 to look at a review of Aquatics Fees and Charges.  These have not been comprehensively reviewed for many years and will involve discussions with all of the organisations and community groups that utilise the pool.  The work is scheduled for completion to advise in the 10 year.

BOTANIC GARDENS

21        Work has recently commenced on the development of a Botanic Garden strategic plan.  The last time the Botanic Garden had a strategic plan was in 2004, and the development of the plan will align with work now underway to review the Botanic Garden Reserve Management Plan.  Staff will be consulting with local runanga, and with a wide range of stakeholders (internal and external) as part of the development of a new strategic plan, and a report will be presented to Councillors in mid-2020.

22        The two weekend Botanic Garden ranger positions are in place.  The Ranger positions provide for staffing at the Botanic Garden over the busiest days of the week (Friday-Sunday).  The ranger’s role is to provide information and advice to visitors, and to patrol the Garden.

OPTIONS

23        No Options

NEXT STEPS

24        Areas of focus for the next quarter will be:

a)      Continuation of the playground safety upgrade works.

b)     Continuation of PARS projects – play spaces, tracks, asset management.

 

Signatories

Author:

Robert West - Group Manager Parks and Recreation

Authoriser:

Sandy Graham - General Manager City Services

Attachments

There are no attachments for this report.


 

SUMMARY OF CONSIDERATIONS

 

Fit with purpose of Local Government

This report relates to providing local infrastructure and it is considered good quality and cost effective.

Fit with strategic framework

 

Contributes

Detracts

Not applicable

Social Wellbeing Strategy

Economic Development Strategy

Environment Strategy

Arts and Culture Strategy

3 Waters Strategy

Spatial Plan

Integrated Transport Strategy

Parks and Recreation Strategy

Other strategic projects/policies/plans

Māori Impact Statement

There are no known impacts for tangata whenua.

Sustainability

The Parks and Recreation activity promotes the social and environmental interest of the community by providing venues and support for sporting and leisure activities, and also provides gardens and open green space that promote the environmental and social interests of the community.

LTP/Annual Plan / Financial Strategy /Infrastructure Strategy

The Parks and Recreation activity is included in the Long-Term Plan.

Financial considerations

The updates reported are within the existing operating and capital budgets.

Significance

This decision is considered of low significance under the Significance and Engagement Policy.

Engagement – external

As this is an update report, and several government and community organisations, and individuals, are involved in some of the key projects described.

Engagement - internal

As this is an update report, and DCC staff from various departments are involved in some of the key projects described.

Risks: Legal / Health and Safety etc.

There are no known risks.

Conflict of Interest

There are no known conflicts of interest.

Community Boards

Matters are discussed with the appropriate Community Board.

 

 


Infrastructure Services

10 February 2020

 

 

Waste and Environmental Solutions Activity Report for the two quarters ending 31 December 2019

Department: Waste and Environmental Solutions

 

 

 

EXECUTIVE SUMMARY

1          This report updates the Committee on Waste and Environmental Solutions operations, maintenance and capital works, including contracted services.

2          Highlights for the two quarters include:

·        Successful partnering between Waste Management and the Waste and Environmental Solutions team has resulted in ongoing improvements at the Green Island landfill, including improved landfill gas collection, increased diversion at the transfer station, installation of new litter fences and odour suppression units, installation of additional leachate control pipework, and improvements to the tipping face access road.

·        Phase Two of the Waste Futures project has progressed on schedule, and a draft economic case with recommended options for public engagement on a future waste collection system was completed and reported to Infrastructure Services and Networks Committee (ISCOM) on 5 August 2019.

·        Technical investigations of the designated Smooth Hill site have confirmed it is suitable for development as a class one waste disposal facility.

·        Technical investigations at the Green Island waste disposal facility have confirmed that the site could remain in operation until 2025/26 if required.

·        A kerbside recycling inspection programme was conducted from September to December 2019, with a total of 3,543 recycling bins inspected at least once.

·        A DCC submission on a Ministry for the Environment Consultation; Proposed priority products and priority product stewardship scheme guidelines, was approved by Council on 1 October 2019.

RECOMMENDATIONS

That the Committee:

a)     Notes the Waste and Environmental Solutions Activity Report for the six months ending 31 December 2019.

 

 

BACKGROUND

3          The Waste and Environmental Solutions activity provides for effective refuse and recyclables collection, resource recovery, and residual disposal in a way that protects public health and minimises impact on the environment.

4          The Waste and Environmental Solutions activity includes:

·        Kerbside collection of waste and recycling for most urban and city residents and small businesses.

·        Disposal Facilities (landfill and transfer station) for waste and Resource Recovery Centre (recycling and reuse store) are provided at Council’s Green Island site. The Waikouaiti site has both a transfer station for waste disposal and recycling facilities. Middlemarch has a transfer station and a hosted community recycling drop-off centre. Waste collected at the community transfer stations is then transferred to Green Island Landfill for disposal. Recycling is sent to the Material Recovery Centre for sorting and transportation to recycling markets.

·        Public place recycling infrastructure and servicing is provided on the streets in the CBD and several satellite locations in the district.

·        Monitoring the state of the Council’s one active and five closed landfills in accordance with the conditions of consents.

·        Monitoring the usage, capacity, and condition of public place waste and recycling infrastructure, CAA cardboard collection services, and kerbside collection services.

·        Education programmes promoting “rethinking, reducing, reusing, and recycling”, cleaner production and sustainable business practice.

·        Auditing and enforcement activities aimed at increasing the quality or quantity of recovered materials.

DISCUSSION

5          Kerbside collection services (refuse and recyclables) are carried out by Enviroway Ltd. in urban Dunedin.  Kerbside collection services in Middlemarch are carried out by a sub-contractor to Enviroway Ltd. 

6          The management and operation of the Green Island landfill is carried out by Waste Management Ltd. The Transfer Stations and resource recovery centres at Waikouaiti and Middlemarch are managed by Waste Management Ltd.

7          The monitoring and reporting for Councils one active and five closed landfills are carried out by GHD Ltd.

8          The emptying of street litter bins, including recycling bins and refuse and recycling collection services in the CBD, and the collection of illegally dumped rubbish, are contracted to McCallum Street Sweeping Services Ltd.

Non-financial performance

Value and Efficiency

9          The LTP performance measures for quantity and quality of diverted material collected via DCC’s collection service is for >2% annual growth in diverted material sold.

10        From June to November 2019 a total of 3799.19 tonnes were diverted (the figure for Dec 19 will not be available until early February).  This total was equal to the same period in 2018, when a total of 3799.60 tonnes was diverted.  Contamination has decreased by 7% from 544.01 tonnes in 2018, to 506.80 tonnes for the same period in 2019.

Major initiatives

11        Waste Minimisation and Management Plan and Waste Assessment - The first Draft WMMP (2020) was presented to Infrastructure Services and Networks Committee in October 2018. The document has been further refined by the WMMP Steering Committee and will be presented to the Planning and Environment Committee alongside the 2018 Waste Assessment on 11 February 2020 for inclusion in the 2020/21 Annual Plan process.

12        Waste Minimisation Grants – Following on from the March round of Waste Minimisation Innovation and Development Grants, it was noted that there was a poor response from commercial businesses. Staff responded to this with targeted engagement and promotion of this grant i.e. connecting with EDU, Start-up Dunedin, Otago Polytechnic, Chamber of commerce and others with an interest in waste minimisation. The outcome of this engagement was;

·    Waste Jam event - Staff meet with Start-up Dunedin and organised an event aimed at lifting commercial interest in waste minimisation and resource recovery ahead of the release of DCC’s Waste Minimisation Grant Package in September 2019. The event was held over 48-hours to rapidly explore ideas, projects, initiatives, and events that encourage, promote, or administer waste minimisation activities. Both the University of Otago and Otago Polytechnic co-sponsored the event. Twelve business concepts where developed over the course of the event.

·    In August 2019 the Community and Culture Committee approved additional funding of $30,000 to the Waste Minimisation Project/Initiatives Grant (increased from $30,000 to $60,000), and $30,000 to the Waste Minimisation Innovation and Development (Commercial) Grant (increased from $40,000 to $70,000), to be funded by the Waste Levy Funds returned to Council from the Ministry for the Environment.

·    Seven commercial waste minimisation applications were received in the September 2019 grant funding round, up from two in the initial March funding round.

·    Following assessment in September, $23,220 was approved for six Community Project applications, and $76,780 was approved for six Commercial applications. To the end of December, $2,500 has been awarded for small waste minimisation projects of $500 or less.

13        DCC Submission on Product Stewardship - A DCC submission on a Ministry for the Environment Consultation; Proposed priority products and priority product stewardship scheme guidelines, was approved by Council on 1 October 2019. Council was in support of the product stewardship submission with minor amendments. Ministry for the Environment staff are now progressing through stage two of the process i.e. the priority product scheme detail.

14        Plastic Free July - Staff co-ordinated with 21 organisations on a programme of events for residents of Dunedin to participate in Plastic Free July. The programme consisted of 26 events including a mix of film screenings, workshops, a panel discussion, environmental market day, and a Plastic Free Lunches programme for schools. In total, 758 people attended these Plastic Free July events. Attendance averaged 76% and received resounding positive feedback.

15        Green Island Landfill and Transfer Station Management – The Landfill Gas collection system has undergone a programme of significant improvements, particularly in the expansion of the gas-field network on the landfill.  The focus of work in this area is now documenting gas destruction for minimising our Emissions Trading Scheme (ETS) costs, and an application for a new Unique Emissions Factor has been prepared for submission to the Environmental Protection Agency (EPA).

16        City Recycling Facilities – Two new facilities are being constructed for the student area to supplement the kerbside recycling service. This is being supported by the University of Otago and Otago Polytechnic, and Polytechnic students have created the initial concept designs. One facility will be located next to the Marsh Study Centre on Castle Street, and the other on the corner of St David Street and Forth Street.

17        An additional Facility is in construction to be located on surplus land owned by the Countdown Dunedin Central Supermarket in Moray Place.

18        Smart recycling and rubbish bins are being trialled as part of a national campaign to reduce litter. Four sets of bins have been installed near the Great King Street Bus Hub, and six sets of bins have been installed in the Warehouse Precinct, as part of the national Let’s Put Litter in its Place campaign. Smart technology can be fitted to the bins that alerts the contractor to empty the bins as required. The design helps to reduce contamination and improve use. The bins have been trialled in other parts of the country where they have demonstrated a significant reduction in contamination levels, and we are seeing similar results in Dunedin. Based on these results this new design will be adopted as standard as existing bins come due for replacement.

19        Composting Made Easy – four public workshops were undertaken in the spring period including one conducted for Syrian migrants living in the Mosgiel area.  

20        Sustainable Living in the Community – a free workshop comprising of several different sustainable living topic options was developed and discussed with some community groups to gauge their interest. To date, we have two suburbs interested in hosting this DCC event for the wider neighbourhood. The one-day event will include; composting at home, community resilience topics (civil defence, healthy homes, food resilience), and sustainable living events. The two events are scheduled for Autumn 2020.

21        WasteMINZ Kerbside Waste and Recycling Audits – National/District - Dunedin is participating in a national kerbside waste and recycling audit which aims to identify customer behaviour related to various types of kerbside collection models (Council and Commercial; bins, bags, and crate collections). The audit also looks at the types of recyclable products being collected and levels of contamination (non-recyclables) entering the recycling collection system. It will also measure the lost opportunity i.e. recyclables disposed in general waste bags and bins. This information will be used to identify effective recycling systems and to improve public communication around recycling and waste collection services. The final national report is expected to be delivered in mid-February 2020.

22        Kerbside Recycling Audits - A kerbside recycling inspection programme was conducted from September to December 2019, with a total of 3543 recycling bins inspected at least once, 1999 bins inspected twice, and 828 bins inspected three times. The audit included the delivery of education material aimed at improving the quality of recyclable material. Unlike previous audits, this inspection programme showed little change from the first to the third inspection and the contamination rate showed only minor improvement. The education and communication material will be revised prior to the next scheduled audit.

23        Recycling Bin latches – An investigation of how we can reduce Yellow lidded recycling bin content from been spilled in adverse weather events (such as high winds) has resulted in a trial of lid latches that will be conducted from January onwards. Communication material has been prepared, and 850 properties in areas prone to high winds have been identified and will have latches fitted to their bins during normal recycling collections.

24        E-Waste and Household Battery recycling – There continues to be a significant increase in some of the targeted e-waste categories since the introduction of subsidised collections rates at the Green Island Rummage store. TVs received for the ten months to the end of September totalled 245 compared to a total of 88 for the 2017/18 year.

25        Bike Refurbishment programme – Up to the end of December 2019, 287 bicycles have been refurbished and gifted back to the community via the Malcam Charitable Trust. The number of bikes dropped off to Rummage still exceeds the amount able to be refurbished. Consideration of alternatives will be investigated.

26        Rummage store improvement plan – A Request for Quotes for refurbishment works on the Rummage store building has been developed. These works involve improved weather tightness, lighting, shelving, painting, and replacement of bird deterrent wire on the roof. The successful contractor will commence works in April with an aim to complete by the end of May 2020.

27        Waste Futures ProjectThe establishment of the Waste Futures project was reported to Council on 26 June 2018.  Progress reports were presented to ISCOM on 15 October 2018 and 11 February 2019, and to Council on 30 April 2019. A further report recommending options for public engagement on kerbside waste and recycling collections was presented to ISCOM on 5 August 2019.

28        Phase One of the project has been completed.  This Phase focused on the Strategic Case and Programme Business Case (PBC) for a future waste and diverted materials system for Dunedin. It also included feasibility studies for operating Green Island landfill until an alternative landfill is available, and investigated the technical feasibility of a new landfill facility at the designated Smooth Hill site.

29        Phase Two of the Waste Futures project has five interlinked Workstreams as outlined in the 30 April 2019 report to Council.  This work is progressing on schedule, and a draft economic case with recommended options for a future waste collection system has been completed.

30        Workstream 1 included a Detailed Business Case to confirm options, levels of service, and procurement models for future kerbside collections and diverted materials systems.  The report to Infrastructure Services and Networks Committee on 5 August 2019 recommended options for kerbside waste and recycling collections and resulted in the following Council resolution:

Moved (Cr Christine Garey/Cr Andrew Whiley):

That the Committee:

 

a)     Approves the two kerbside collection options for community feedback:

i)          a wheelie bin for rubbish collection in addition to the existing recycling system; and

ii)         a wheelie bin for rubbish collection, plus another wheelie bin for organics collection, in addition to the existing recycling system.

b)     Notes the preliminary community engagement process, to seek feedback on options, will occur during the 2020/21 Annual Plan process.  

c)     Notes that the results from this preliminary community engagement process will be used to inform options for full consultation in 2021 as part of the 10 Year Plan. 

Motion carried (INF/2019/033)

31        Workstream 2 included the investigation of options to preserve or extend the capacity of Green Island landfill, plus develop contingency plans for managing waste if Green Island landfill capacity is exhausted before Smooth Hill landfill is operational. The short-listed options are now in the process of being implemented and it is expected that the Green Island waste disposal facility could remain in operation until 2025/26 if required.

32        Workstream 3 included detailed work to confirm the suitability of the designated Smooth Hill site for a Class 1 waste disposal facility. Technical site investigations and the gathering of all necessary information to complete a detailed Assessment of Environmental Effects (AEE).

33        The proposed Smooth Hill site was originally recommended as a replacement for the Green Island landfill in the early 1990’s after extensive evaluation of 32 potential sites, and subsequently approved by Council for detailed investigations on 4 February 1992. Public consultation was carried out in March 1992, and again in November 1992 through to February 1993, with the final recommendation approved by Council on 21 April 1993. The notice of requirement for the site designation was first notified on 24 July 1995, and then re-notified on 19 July 1999, with the District Plan becoming operative on 19 April 2004, including all designations.

34        Site investigations are now substantively complete and has confirmed the suitability of the Smooth Hill site. An AEE is now being prepared for lodgement alongside the consent applications in April / May 2020. The consenting process will be publicly notified and is expected to take 18 – 24 months to complete.

35        In order to enable the development of the Smooth Hill site as a Class 1 waste disposal facility it will be necessary to negotiate with landowners adjoining the site itself, and in particular McLarens Gully Road, for the purchase of additional parcels of land. McLarens Gully Road will require re-alignment and widening, including modifications to the intersection with State Highway 1, in order to create a suitable approach road and entranceway into the Smooth Hill site. These negotiations are scheduled to begin in February 2020.

Capital projects

36        Projects include:

·      Green Island Landfill - Improvements to Final Cap, Transfer Station and Rummage Store, Leachate collection system, Gas Collection system, and traffic flow

·      Green Island LandfillConstruction of new tipping face access road

·    Green Island Landfill – Installation of second weighbridge and new security system

·    Waikouaiti Landfill – Final capping

·    Waikouaiti Transfer Station – redevelopment

·    Middlemarch Transfer Station - redevelopment

·    Additional City Recycling Facilities

OPTIONS

37        As this is an update report, no options are provided.

NEXT STEPS

38        Areas of focus for the next quarter will be:

·        Procurement for a re-aligned access road onto the active Green Island landfill face which will unlock the next 2 stages of landfill. This will also deal with the Asbestos soils area, as well as improving our management of leachate and landfill gas in this area

·        Detailed planning, design, and procurement for installation of a second weighbridge at Green Island Landfill, including associated weighbridge software, improvements to traffic flow, and improvements to site security

·        Progressing phase two of the Waste Futures project to fully develop the detailed business case on options for DCC’s future waste services operating model for inclusion in the 10-year plan 2021-31

·        Implementation of options for the preservation of capacity at Green Island landfill will continue

·        Detailed design and procurement for the final capping of the Waikouaiti landfill and improvements to the Waikouaiti Transfer Station, Resource Recovery Centre and Closed Landfill, in collaboration with the local community

·        Working closely with the University of Otago and Otago Polytechnic to install recycling drop off facilities in the student area to supplement kerbside recycling services

·        Working closely with Countdown Dunedin Central Supermarket to install an additional city recycling drop off facility

·        Incremental improvements to the Green Island Landfill gas collection system will continue.

 

Signatories

Author:

Chris Henderson - Group Manager Waste and Environmental Solutions

Authoriser:

Simon Drew - General Manager Infrastructure Services

Attachments

There are no attachments for this report.

 


 

SUMMARY OF CONSIDERATIONS

 

Fit with purpose of Local Government

This report relates to providing local infrastructure that is considered good-quality and cost-effective.

 

Fit with strategic framework

 

Contributes

Detracts

Not applicable

Social Wellbeing Strategy

Economic Development Strategy

Environment Strategy

Arts and Culture Strategy

3 Waters Strategy

Spatial Plan

Integrated Transport Strategy

Parks and Recreation Strategy

Other strategic projects/policies/plans

 

The Waste and Environmental Solutions activity supports the outcomes of a number of strategies.

 

Māori Impact Statement

There are no known impacts for tangata whenua.

 

Sustainability

The Waste and Environmental Solutions activity contributes positively to the environmental interests of the community through refuse and recycling collection at the kerbside and public places, educating and promoting environmentally sustainable behaviour and managing landfill and transfer station facilities.

 

LTP/Annual Plan / Financial Strategy /Infrastructure Strategy

The Waste and Environmental Solutions activity is included in the Long-Term Plan.

 

Financial considerations

The updates reported are within existing operating and capital budgets.

 

Significance

This decision is considered of low significance under the Significance and Engagement Policy.

 

Engagement – external

As an update report no external engagement has been undertaken.

 

Engagement - internal

As an update report no internal engagement has been undertaken.

 

Risks: Legal / Health and Safety etc.

There are no identified risks.

 

Conflict of Interest

There are no identified conflicts of interest.

 

Community Boards

Any issues are discussed with the appropriate Community Board.

 

 

 


Infrastructure Services

10 February 2020

 

 

Property Services Activity Report for the two Quarters Ending 31 December 2019

Department: Property

 

 

 

EXECUTIVE SUMMARY

1          This report updates the Committee on Property Services operations, maintenance and capital works for the two quarters 01 July 2019 to 31 December 2019.

2          Highlights for these quarters include:

a)         Palmyra redevelopment is confirmed and commencing in February 2020.

b)        Wall Street Mall management outsourced to Colliers International is confirmed with a start date 01 October 2019.

RECOMMENDATIONS

That the Committee:

a)     Notes the Property Services Activity Report for the six months ending 31 December 2019.

 

BACKGROUND

3          Property Services aims to provide ‘community good’ through effective management of property assets for the city of Dunedin. Property Services manages five property portfolios; community housing; investment property; commercial property; operational property; and community property. There is also a separate endowment property portfolio.

4          The Property Services activity also includes:

·    Land and lease management,

·    Facilities and asset management,

·    Project management, and

·    Tenancy management.

DISCUSSION

Management of Property Services

5          The Property Services group is responsible for a wide range of Council-owned properties.  The group manages land and tenancy, acquisition and disposal of properties to meet the Council’s needs, facilities and asset management, and management of housing.

6          The community housing portfolio provides affordable housing primarily targeted at those on low incomes, aged 55 and older.  In addition to the community housing units, this portfolio includes a small number of residential properties that have been acquired by the Council in relation to its operational activities.

7          The investment portfolio includes a small number of commercial properties that are owned for the purposes of generating a financial return. They are listed as “investments” for accounting purposes only.

8          The commercial portfolio includes a number of commercial properties that are owned for the purposes of generating a financial return. They are managed in the same way as the investment portfolio and treated differently for accounting purposes only.

9          The operational portfolio includes property and related land that are required for service administration and delivery purposes by the Council.

10        The community portfolio includes a range of properties that are held for community benefit, but not directly used in the delivery of council services – for example, the Dunedin Railway Station, Regent Theatre, and community halls.

Service and Satisfaction

The housing provided by the Council meets the needs of the community housing tenants

Percentage of tenants satisfied with Council provided rental housing

11        Every resident is visited annually and as part of the process they are surveyed on how well their housing meets their needs. In this survey, tenants are asked to rate how well the housing meets their needs and are invited to provide comments.

12        Between 1 October 2019 and 30 December 2019 (Quarter 2) 137 tenants were surveyed and 96% of our tenants completed the survey.  Of those that responded, 92% of our tenants said the “housing meets or exceeds their needs”.

13        Comments from respondents who indicated the “housing exceeded their needs” were very positive about the location of their unit as well as how functional, affordable and warm and dry their unit is.

14        4% of our tenants indicated their housing did not meet their needs.  This was primarily due to disability related needs, such as requiring a shower rather than a bath or additional hand rails. Our Tenancy Managers investigate and follow up all situations where feedback indicates the housing does not meet the tenants’ needs and 4% of tenant’s did not complete the survey.

Percentage occupancy of Council provided rental housing

15        To ensure the community housing portfolio is meeting demand, and turnover time between tenancies is minimal, occupancy rate is measured as a percentage of occupied time versus available time.

16     Occupancy remains high at 97% as at 30 December 2019.  There are currently 17 vacant units, of which three units are under offer to new tenants and three units are in the process of having renovation works completed. 

17     The Housing Team have completed temporarily relocating eight tenants who reside in block one in our Palmyra public housing complex, while substantial redevelopment work is completed at this site in February 2020.  This will affect our occupancy rates slightly over the upcoming months.

Number of occupancy changes in community housing

18    The number of community housing units that are vacated over time reflects the volume of work for the Tenancy Managers when tenancies end; formalising the end of a tenancy, organising changeover work, and settling in new residents.

19     Numbers of tenants vacating are in line with previous years and no seasonal trends are identified.

20     The housing team have recently started recording the reasons why our tenants vacate. Evidence indicates most vacancies arise due to a death of the tenant or the tenant going in to care.  Also, more recently a number of tenants have vacated due to transferring to another DCC unit. This is a result of substantial redevelopment work e.g. at our Palmyra complex.

Waiting list for community housing

21     The waiting list is measured to understand the demand for community housing. This is taken as the number of applicants currently on the waiting list at the end of each calendar month. 

22        As at 30 December 2019 the waiting list was 282.

23        The waiting list has been steadily increasing as more applicants are added to the waiting list than are able to be placed each month.  We have taken 42 new applications over the last quarter and been able to house 10 new applicants over this period of time.

24        Almost 30% of the applicants currently on our waitlist have received an offer of housing at some stage, which they have declined.  The Housing Team have started recording all offers of housing current and historic, including those offers which are declined.  This will to allow us to better understand the reasons for declined offers and also assist our future thinking.  We have also started a thorough review of our waitlist, in order to better understand our applicants’ current circumstances and their level of housing need.

Community housing rental income

25        Community housing tenants pay rents according to the published schedule that relates to the size of the unit.  

26        Rental income for Community Housing typically remains steady as the occupancy rate remains steady. There were three fortnightly payment cycles in August 2019.

27        Rental income for October includes the sale of 113 Harbour Terrace.

Council investment properties are appropriately managed

Percentage overall occupancy of Council investment properties

28        The investment portfolio managed by Property Services, serves as a non-rates revenue stream. Occupancy rate is measured as a percentage of tenanted units versus available lease units.

29        The investment portfolio contains 16 properties, broken down in to 50 lease units. 44 of these are currently occupied.

30        Three lease units have been vacant since October 2019 on Parry Street, though short-term agreements are in place for two of the units until a long term tenant is found.

31        Two lease units at 54 Moray Place are currently advertised for lease following completion of compliance upgrades. Active enquiry is currently being fielded.

32        There is one additional vacancy at 211 George Street (Wall Street) currently advertised for lease.

33        Ten leases are due to expire in the 12-month period to 31 December 2020, these will be managed proactively to minimise vacancy where tenants do not elect to either renew (where rights of renewal exist) or enter into a new lease term.

34        Of note, Bunnings Limited has confirmed the six-year renewal effective 14 December 2019 for Council’s Porirua property. Lease negotiations are progressing. 

Revenue of Non-Housing Properties

35        Revenue is generated from non-housing properties through rent payments, OPEX recoveries, and rates.

36        Following an increase in OPEX recoveries from 1 July 2019 upon commencement of the new financial year, Non-Housing Revenue has remained steady.

37        Non-Housing Investment portfolio revenue reflects a change of tenant at 20 Parry Street, November 2019.

Value and Efficiency

Council operational properties are appropriately managed

Percentage of service request resolution times met

38        Completion of scheduled work continues to achieve higher than target performance.

39        Almost 4,000 scheduled work orders were due for completion during the quarter. Around two-thirds of scheduled work orders relate to the Community Housing portfolio.

Number of Reactive Work Initiated

40        Property Services offer reactive maintenance service to managed properties. The level of reactive work required is measured by the total number of reactive work orders initiated in a given month.

41        Reactive maintenance work volumes reduced by 5% year-on-year during the Oct-Dec period, continuing the trend from the first quarter.

42        December reactive work volumes demonstrate seasonal reductions due to the Christmas holiday period.

Number of Planned Preventative Maintenance Work Required

43        Property Services carry out regular planned preventative maintenance (PPM) to managed properties to maintain the service life of assets. The level of PPM work required is measured by the total number of PPM work orders due in a given month.

44        For the Community Housing portfolio, the number of PPM work orders raised is directly related to the number of housing properties to be maintained to the required standard.

45        Six  facilities account for just over half of all PPM work for non-housing properties. These are the Dunedin Public Art Gallery, Civic Centre, City Library, Wall Street Mall, Dunedin Railway Station and the Municipal Chambers / Town Hall complex.

Major initiatives

46        Major Initiatives:

a)         South Dunedin Library & Community Complex: WSP Opus have now been engaged and will head up the design team for this project. Co-design process is progressing and is in the discovery stage, about to move to the concept stage. Four options for the site were developed and costed, design team are now moving along with a phased approach to the design and eventual construction of the project.

b)        Edgar Centre: Seismic strengthening work is well advanced in the More FM arena, with work about 2 weeks ahead of schedule.  Work here is due to be completed by the end of February 2020

c)         School Street: Ten new housing units to be built, demolition of the site has commenced however has been held up due to the presence of asbestos. While the presence of asbestos was known and was planned for during the demolition additional soil contamination has been discovered at various locations on the site. Demolition is now expected to be completed by the mid to end of February 2020.

d)        Toitū: Construction to replace various roofing issues on the older buildings of the site is progressing well. Asbestos has been discovered and pushed out the finishing date of the project.

e)        Municipal Chambers, Town hall and Railway station: Conservator architects have been engaged to produce tender documents to effect repairs to the exterior of all buildings.

f)         Civic Centre and Library Lifts: All six new lift have now been installed in both buildings and are operational.

g)         Mosgiel Library: Construction is almost complete, the new roof has been installed together with the electrical switchboard, fire alarms and lighting. The only outstanding item is the new air conditioning system.

h)        Palmyra – 38 public housing units to be renovated – Upgrade of existing housing, 4 blocks of flats with the first blocks being stated in February 2020 and all blocks completed by December 2022. The upgrade consists of insulation, new roofing membrane, hew electrical switchboard, new fire alarm and emergency lighting. We are installing new double glazing, laundry / bathroom replacement, asbestos removal together with pipe replacement and exterior repairs.

OPTIONS

47        As this is an update report, there are no options.

NEXT STEPS

48        Areas of focus for the next quarter will be:

 

a)         South Dunedin Library & Community Complex: Continue with the co-design process, going from discovery phase to concept stage. Investigations will commence in the existing buildings, looking at asbestos and compliance upgrades. Design team will focus on concept design, project will be staged over a number of years, the staging plan is in development and should be completed by the end of the quarter.

b)        Edgar Centre: Structural strengthening to the More FM Arena will be complete by the end of February. The Edgar Centre will no longer be classed as Earthquake prone.

c)         Edgar Centre: The design team will be assessing the differential settlement issues at the Edgar Centre with the aim to identify the preferred solution to resolve or mitigate those issues. The feasibility study will be due in mid-February 2020, with any design works for the preferred solution to follow.

d)        School Street: The soil asbestos will be removed mid-February 2020 with the remaining flats demolished and site cleared. Foundation works will commence and building of the new housing units and flats will start. With delays due to asbestos works construction to be complete in the second quarter of 2020/21 financial year.

e)        Palmyra: Construction work will commence in February 2020 and will be completed by December 2020 for the first two blocks.

f)         Railway station: 1st stage design completed and tender out for the exterior repair work to a main contractor, work scheduled to commence in March / April 2020.

g)         Mosgiel Library: New roof, air condition and services, this project will be complete early February 2020.

h)        Tarpits – Submerged redundant tar waste tank. A consultant has been engaged to assist DCC Property Services to develop tender documents to engage contractors to remediate the tank and its contents.

 

 

Signatories

Author:

David Bainbridge - Group Manager Property Services

Authoriser:

Sandy Graham - General Manager City Services

Attachments

There are no attachments for this report.

SUMMARY OF CONSIDERATIONS

 

Fit with purpose of Local Government

This decision promotes the social well-being of communities in the present and for the future.

Fit with strategic framework

 

Contributes

Detracts

Not applicable

Social Wellbeing Strategy

Economic Development Strategy

Environment Strategy

Arts and Culture Strategy

3 Waters Strategy

Spatial Plan

Integrated Transport Strategy

Parks and Recreation Strategy

Other strategic projects/policies/plans

 

The Property Services activities support the outcomes of a number of strategies.

Māori Impact Statement

There are no known impacts for tangata whenua.

Sustainability

The Property Services team actively contributes positively to the interest of the community by providing and maintaining property required for a wide range of community, housing, Council operations, arts and culture, sport, and heritage service purposes.

LTP/Annual Plan / Financial Strategy /Infrastructure Strategy

Property Services activities are included in the 10-year plan.

Financial considerations

The updates reported are within existing operating and capital budgets.

Significance

This decision is considered of low significance under the Significance and Engagement Policy.

Engagement – external

As an update report, external engagement is not applicable.

Engagement - internal

As an update report, internal engagement is not applicable.

Risks: Legal / Health and Safety etc.

There are no legal or health and safety risks.

Conflict of Interest

There are no conflicts of interest.